The new 875-bed Lisboa Oriental hospital will not open until 1 December 2029. Its budget has risen to €899 million
The government has set a new opening date for the Hospital de Lisboa Oriental (East Lisbon hospital): 1 December 2029. The Council of Ministers also raised its spending ceiling to €898.9 million excluding VAT (Council of Ministers statement, ECO).
The 875-bed hospital is being built in Marvila. Six old hospitals in the city centre, now part of the ULS São José local health unit, will move there: São José, Santa Marta, Dona Estefânia (the children's hospital), Curry Cabral, Capuchos and the Alfredo da Costa maternity hospital. Until the new hospital opens, patients will continue to be treated and babies delivered in the old buildings, many of which are more than a hundred years old.
The new hospital has been a long time coming. It was declared a priority back in 2008, and the tender was launched in 2017 with a base price of €334.5 million. A consortium led by Mota-Engil is building it and will then run its maintenance under a public-private partnership contract. Construction began in early 2025.
Because of the delays, Portugal lost €100 million that the European Recovery Plan had set aside for the hospital. The government has now recalculated the costs and spread them over several years: the €898.9 million includes almost €25 million already spent over the past two years. The consortium, for its part, has agreed not to claim further compensation from the state for technical and geological problems on the site.